Sept 13th – 20th : Road Works : Hayes Lane to Uplands Road

At our last pre Covid AGM a member suggested that we ‘get on with resurfacing the (Welcomes) Road instead of just talking about it’. Having received quotes from Swift Surfacing, TTS Surfacing and London Surfacing Co Ltd. The latter company came with an informal ‘introduction’ from the Council Highways Dept. We met the various personnel from each of these companies and the result was that we felt we could work best with the road engineer (Chris) from London Surfacing Co. Ltd. Each quote was similar in terms of price. Anyway we are now ‘getting on with it’ by making a start with resurfacing the section of Welcomes Road from Hayes Lane to Uplands Road (Phase 1). Phase 2 will cover Uplands to Zig Zag Road (2022) and Phase 3 from Zig Zag to Kenley Lane when construction traffic has tailed off.

To be clear : the road will be closed at the Uplands Road junction on the south side and at the Hayes Lane end near the white posts. Traffic from the Welcomes Road from the north (lower end) will be able to turn right into Uplands Road.

Specification : The intention is to apply an overlay of 40mm of stone mastic asphalt (SMA) after regulating the existing surface and re-profiling one speed ramp and installing a drain pipe by the top ramp near Hayes Lane. The works include a 12 months guarantee.

The impending works will commence on Monday 13th September 2021 for 5 days as follows, with working hours from 9am to 5pm :

Monday 13th
NO PARKING ON ROAD
Set up site and start the following prep works, Adjust iron work and install drainage pipes. Cut joints at all tie in points.
Road open but with traffic management.

Tuesday 14th
Preparatory works
Road open but with traffic management

Wednesday 15th to Friday 17th
Start resurfacing works from Hayes Lane working towards Uplands Road laying in 3 stages over this period.
ROAD WILL BE CLOSED WEDNESDAY TO FRIDAY WITH SOME ACCESS AFTER 5 PM.

Monday 20th September
Install new speed ramp between Maryhill Close and Simone Drive near telegraph pole. Carry out line marking.
Road open but with traffic management.

IMPORTANT

Members fronting Welcomes Road between Uplands Road and Hayes Lane will need to bear in mind that the contractors need to be allowed to get on with their work uninterrupted. When the overlay is being applied it is vital to keep away from moving machinery. Walkers should be able to find a way round the road works but are encouraged to keep away from the site. If you need to use your car please park it on Uplands Road considerately but do not park near the junction with Welcomes Road as this area will be set aside for the contractors plant and machinery. The postman will need to walk to houses having parked in Uplands Road and other deliveries avoided that week unless essential.

If you have space on your drive for an extra car please let me know  in case any of the  people who will lose access to their own drives from Wednesday 15th to Friday 17th could use it. Otherwise parking will need to be in Uplands Road or other public roads nearby. The section of Uplands Road leading to the junction with Welcomes Road will be reserved for the contractor’s plant and machinery.

SMA curing time 24 hours. No HGV traffic during this period.
Monday is, of course, a refuse collection day for food waste and plastic. This should take place before 9am when the contractor starts work each day.

Site Manager: Chris Stylianou Mobile 07808 318328. Please approach Chris if you need help.
Other contact Nos. Colin Brown 020 8668 2101, Richard Russell 07563 723809 and 020 8668 7293.

PLEASE BE PATIENT WHILE THE WORK PROCEEDS.
Working in Welcomes Road is never easy and your patience will be appreciated

MANY THANKS.