Zig Zag Road junction roadworks – 16th to 21st Dec

Please avoid using the Zig Zag Road/ Welcomes Road junction from between Wednesday 16th and Monday 21st December. 

The very informal logistics plan is as follows:

1. Wednesday 16th December at about noon the contractor will start to gun off the surface of the road in the bellmouth of Welcomes Road and 5m into Zig Zag Road

2. Thursday and Friday 17th and 18th December the work will continue and  concrete edging installed along  the hedge line fronting Zig Zag Road and which belongs to 70 Welcomes Road.  The new edging will support the compaction of the new tarmac.

3. Saturday and Sunday the junction will be CLOSED to vehicular traffic to allow the new surface to ‘go off’. No motorised traffic particularly HGVs must drive over the new surface for 48 hours.

4. Early Monday morning the contractor will remove signage  closing the road so the refuse lorry can pass.

The contractor will be allowing traffic to use the junction from Wednesday to Friday but for safety reasons if you can avoid the junction by using Abbots Lane and Uplands Road that would be very much appreciated.

The road will be passable to pedestrians at all times including over the weekend. Apologies for the short notice but these jobs are very much dependent on when the road materials become available.

Construction Site Contacts

These are the contact details for the first point of contact for any issues you may have regarding the construction sites currently operating on the WURA roads under planning applications approved by Croydon Council.

Please only refer back to the WURA Secretary if you are not satisfied with the developer’s response to your enquiry.  Please copy the Secretary in on any correspondence for record keeping purposes. Note also that if you are unhappy with the response and believe that the developer has broken the terms of their agreements, you should raise the issue with Croydon Council as described in “Problem With Construction Sites” .

32 Welcomes Road – Goldstone Homes

Site Manager: Phil Johnson
T: 07534 506 244
E: phil@goldstonehomes.co.uk
W: www.goldstonehomes.co.uk
Construction Logistics Plan: 32 Welcomes Road
Routing Map: here

42 Welcomes Road

Admin Manager: Mr Joy Gopinadhan
T:07703 209 652
E: joy@phoenix-lr.com
Construction Logistics Plan: 42 Welcomes Road

57 Welcomes Road – Regal Abode Ltd

Admin Manager: Abi Mukhurjee
T: TBD
E: estate.manager@mail.com
Construction Logistics Plan: 57 Welcomes Road

35 Uplands Road – CPSL Construction Ltd

Admin Manager: Mr Darryl Castelino 
T:07540 369293
E: TBD
Construction Logistics Plan: 35 Uplands Road

Others

36 Welcomes Road is now complete and occupied.